Call before you dig - It's the LAW.
Remember: Call the OUNC at least two business days before you dig
PRESS RELEASES
 


December 2007


Golden Shovel Award to be presented at the Central Oregon \ R.E.L.U.

::top::


July 2006

Oregon Utility Notification Center
Chapter 952

Rule Caption: Updates and clarifies definitions and rules regarding utility locate requests and markings.

Date: Time: Location:

8-8-06 9:30 a.m. Public Utility Commission
Small Hearing Rm., 2nd Flr.
550 Capitol St. NE
Salem, OR

 

Hearing Officer: Allan Arlow

Stat. Auth.: ORS 183 & 757, Sect. 105 & 8, Ch. 691 OL 1995

Stats. Implemented: ORS 757.542 & 757.552

Proposed Amendments: 952-001-0010, 952-001-0050, 952-001-0070

Last Date for Comment: 8-8-06, 5 p.m.

 

Summary: This rulemaking updates and clarifies the definitions used in the Utility Notification Center Administrative Rules. The amendments also clarify and update the rules regarding excavators giving notice of proposed work and the marking of underground facilities.

 

Rules Coordinator: Diane Davis

Address: Oregon Utility Notification Center, 550 Capitol St. NE, Suite 215, Salem, OR 97301-2551

Telephone: (503) 378-4372

Notice of Proposed Rulemaking Hearing

::top::


 

March 3, 2003

 

ERROR IN THE LAW- OPUC and Department of Justice Issue Administrative Ruling Clarifying Agricultural Exemption


During the current Energy Facility Siting Council hearings on the Application for a Site License for the South Mist Pipeline Extension Project, there has been some confusion regarding the Oregon excavation laws as they relate to agricultural practices. There is an error in the current excavation law that is responsible for the confusion, and this letter is being provided to explain and clarify the problem and resolve the issue.

 

The original 1987 excavation law specified that a request for locates must be made two business days prior to any excavation activities. However, that law provided an exemption for agricultural tilling, as defined in the Department of Agriculture statute, ORS 215.203(2). The law also limited the exemption to a working depth of 18 inches. In other words, the farmer was not required to request locates if plowing, disking, etc. did not exceed 18 inches, but if any work would exceed 18 inches, then a request for locates was required. The 18-inch exclusion depth is nearly a universal specification in the United States.

 

When the current excavation law was written in 1995, the agricultural exemption was carried forward into the new law, with one difference. The Legislative Committee decided to drop the 18-inch specification because if the Agriculture Department ever changed the tilling depth definition, we would have to go into rule-making hearings to conform our rules. By simply deferring the specifics to their statutes, we would not have to change our rules.

 

The problem surfaced a few months ago when it was discovered that the Department of Agriculture statute, referenced in the excavation laws, is non-existent as related to the definition of tilling. There is no clear explanation of what happened, but it is clear that the original error was brought into the current law.

 

However, the resolution of this issue is clear. The PUC and the DOJ will interpret and enforce the 18-inch exemption, as it was clearly the spirit and intent of the law to provide that exemption for farmers. Otherwise, farmers would now be required to request locates for any work exceeding 12 inches. That would be burdensome and unrealistic for the farming community. Therefore, it is our intent to retain the 18-inch exemption until such time that Administrative Rules Hearings are held to formally specify the exemption.

 

The excavation laws are designed to protect the public and all buried facilities, not just pipelines. There are a large number of facilities buried throughout Oregon, and many of these facilities are not buried as deep as gas pipelines and that is the primary reason that the exemption is limited to 18 inches.

 

For normal tilling operations of less than 18 inches, the excavation laws do not require farmers to request locates. However, when a request for locates is required, there is absolutely no cost involved; the phone call to the one-call center is toll-free and there is no charge for the locate markings. The only “burden” is that advance planning is needed because there is a two-business day waiting period before excavation can begin. The waiting period is necessary to allow the facility operators time to locate their facilities and provide the markings.

 

I trust this clarifies the situation and provides stability to the Oregon excavation laws. If you have any questions, or wish to discuss any of these issues further, please feel free to contact me.

 

Jack P. Dent
Chief, Pipeline Safety
503-378-6760
jack.dent@state.or.us

 

::top::


Thursday, March 13, 2003

 

Oregon Utility Notification Center
1415 SE Ankeny St.
Portland, OR 97214
503-232-1987

 

For Immediate Release

 

Contacts:

Jack Dent, Chief, Pipeline Safety, Oregon Public Utility Commission
(503) 378-6760; jack.dent@state.or.us

Gary Hyatt, Chair, OUNC Publicity & Education Committee
(503) 585-6611 x 8166; gfh@nwnatural.com

 

Do you know Where Your Pipes Are?
Utility experts warn of underground hazards

 

PORTLAND, OREGON - Homeowners and excavators are advised to dig responsibly by calling the state's One-Call number to have underground lines marked with color-coded paint. The Oregon Utility Notification Center's (OUNC) toll free number is 1-800-332-2344. This is a free service provided by utilities statewide.

 

Buried beneath your feet lies a complex web of electric, natural gas, oil, fiber-optic, telephone, cable-television, water and sewer lines. One wrong move might cause hundreds or thousands of residents to be cut off from heat, electricity, telephones, 911 calls, and other vital services. When you make the call, the One-Call Center notifies affected facility operators. With the ground marked in your work area, you have taken the first step to avoid damage or injury.

 

"Many people are surprised to learn calling for locates is not just a good idea - it's also the law," says Jack P. Dent, Chief, Pipeline Safety, Oregon Public Utility Commission. By Oregon law, everyone planning an excavation project must call the toll free number and wait for the lines to be marked. Failure to make the call subjects the excavator to liability for accidents and potentially, fines.

 

Homeowners and contractors using power equipment subject themselves to tremendous liability and risk if they fail to make the call and follow the rules.

"By the time you realize you've hit something, it's too late to prevent damage. Even a shovel can cause a surprising amount of damage," says Dent.

 

Whether you're planting flowers, putting in a sprinkler system or building a new deck, there are four important steps to Dig Safely.

 

The first step is to call the Oregon One-Call Center at least two business days before beginning your digging project. The toll-free number is 1-800-332-2344. The One-Call center will notify the facility operators, who will then take care of marking the property for underground utilities. The second step is to wait for the lines to be marked with color-coded paint. The third step is to respect the marks, and the final step is to dig with care.

 

For more information, call the Oregon Utility Notification Center at (503) 232-1987. Now the Oregon Utility Notification Center's has information on-line at www.digsafelyoregon.com. Remember, safe digging begins by calling 1-800-332-2344. Call before you dig and keep yourself safe.

 

::top::



Counterpoint - Northwest Natural Pipeline Siting: Public Right-of-Way Versus Exclusive Farm Use Land

Jack P. Dent
Chief, Pipeline Safety
Oregon Public Utility Commission

Northwest Natural's (NWN) request for a site license for the proposed pipeline route from Mist to Molalla has stirred up a recurring controversy. Larry Briggs detailed the controversy in the Oregonian on May 16th. The issue is whether the proposed pipeline should be placed in the public right-of-way or in land zoned as Exclusive Farm Use (EFU).

 

The Oregon Public Utility Commission (OPUC) has jurisdiction over the design, construction, testing, operation & maintenance and emergency response activities for all intrastate natural gas pipelines in Oregon, but it does not have authority over the siting of these pipelines. That is the responsibility of the Energy Facility Siting Council (EFSC).

 

Siting pipelines in the public right-of-way along streets and roads raises safety issues. Many cities and counties require that all utility lines be installed underground. There is a finite amount of public right-of-way available for the utilities, and we are simply running out of room. The rights-of-way are becoming a bewildering jumble of active-service cables, pipes, and conduits as well as abandoned facilities. Pipelines in this chaotic real estate explain why excavation damage is the leading cause of pipeline failures. The right-of-way should be the site of last resort rather than the first. However, trying to find a contiguous 50-mile corridor of EFU farmland is clearly out of reach, and putting the pipeline into a public right-of-way in limited areas is inescapable. Northwest Natural has obtained private easements wherever possible in an effort to avoid the public right-of-way. EFSC becomes involved when a private easement cannot be obtained from a willing landowner, and NWN must clearly demonstrate that using the public right-of-way presents an unreasonable risk. Putting the pipeline in the right-of-way does not make the pipeline inherently hazardous; it just means that the pipeline is at a higher risk than if it was in EFU.

 

I would prefer that pipelines be installed in less densely populated areas for obvious reasons, but I don't believe that a pipeline should be prohibited in areas that are "targeted" for growth. The problem that I see is in basing a decision today on something that may or may not happen in the future. If the pipeline is built before the high-density growth occurs, then I believe that it is incumbent upon the planning commissions to prevent encroachment on the pipeline, and to enforce the pipeline easement boundaries.

 

EFSC has an enormously difficult task in balancing everyone's interests, but in the final analysis a decision must be made as to where to site a pipeline. The final decision will probably not please all parties, but the EFSC will make its decision based on the laws of this state and the facts, as EFSC members see them.

All types of pipelines (gas and liquid) have been constructed in farmland for decades, and there are compelling reasons why. Farmland is viewed as a true resource that must be protected from development or conversion to other types of land uses. That EFU land is rarely rezoned provides protection for the pipelines from the leading cause of pipeline failures: excavation damage. Conversely, the existence of a utility easement running through farmland makes that land less attractive to developers, which then helps protect the status of our EFU lands. Despite comments to the contrary, pipelines do not affect crop productivity (excluding certain tree crops) if the soils are replaced properly as required by the site license.

 

To combat the risk associated with excavation damage, the 1995 Oregon Legislature created the Oregon Utility Notification Center (OUNC) commonly known as the "Call Before You Dig" center. Oregon law requires that all operators of buried facilities must register their facilities with the OUNC and that all excavators call the OUNC (800-332-2344) two business days before digging. Using a digitized mapping system, the Center can determine what buried facilities are present at the excavation site and notify the affected operators of the impending excavation. This waiting period allows the operators to get to the proposed excavation site and accurately mark their facilities so the excavator is aware that there are buried facilities in the area of the excavation. The OPUC is charged with enforcing violations of the excavation laws through civil penalties. For additional information about this important Center, visit our Web site at www.DigSafelyOregon.com.

 

Siting pipelines is a difficult job, where public safety must be weighed against the rights and convenience of landowners. Oregon's Energy Facility Siting Council conducts the balancing process where those decisions are made, and all interested citizens are encouraged to make their viewpoints known to EFSC, so that their decisions can be the best possible for all Oregonians.

 

This article appeared in the editorial section of the Oregonian newspaper.

 

::top::


Wednesday, April 24, 2002

 

Oregon Utility Notification Center
1415 SE Ankeny St.
Portland, OR 97214
503-232-1987

 

For Release, Wednesday, April 24, 2002

 

Contacts:

Jack Dent, Chief, Pipeline Safety, Oregon Public Utility Commission
(503) 378-6760; jack.dent@state.or.us

Gary Hyatt, Chair, OUNC Publicity & Education Committee
(503) 585-6611 x 8166; gfh@nwnatural.com

June is 'Dig Safely' Month in Oregon

Governor proclaims it's everyone's responsibility to dig safely

 

SALEM, OREGON - Homeowners, contractors and excavators are reminded of Oregon's excavation laws during the month of June. Proclaimed "Dig Safely Month" by Governor John A. Kitzhaber, June is a month with a notable increase in excavation work around the state.

 

In a typical neighborhood, a complex web of utility lines lie buried under lawns, sidewalks and driveways. When digging, one wrong move might cause hundreds or thousands of residents to be cut off from heat, electricity, telephones, water, 911 calls, and other vital services. When you make the free call to the One-Call Center, they notify utilities to mark the ground with color-coded paint. After the utilities are marked in your work area, you have taken the first step to avoid damage or injury.

Calling before you dig and digging safely not only prevents damage, but is also the law! Oregon state law requires homeowners, contractors and excavators to contact the One-Call Center at least two business days before digging. "Taking care where you dig with a shovel or backhoe can not only prevent damage to underground utilities, but the potential loss of life as well," says Gary Hyatt, Volunteer for the OUNC. Hyatt is the chair of OUNC's Publicity and Education Committee. "The Governor's proclamation is testimony to the importance of safe digging," notes Hyatt.

 

These four appropriate steps ensure an excavation project is free of preventable damage:

  • The first step is to call the Oregon One-Call Center at least two business days before beginning your digging project. The toll-free number is 1-800-332-2344. A One-Call representative will notify the facility operators, who mark the property for underground utilities with color-coded paint;
  • The second step is to wait for the lines to be marked with color-coded paint;
  • The third step is to respect the marks, and;
  • The final step is to dig with care.

The "Dig Safely" campaign is the centerpiece of the Oregon Utility Notification Center's (OUNC) efforts to increase public awareness of Oregon excavation laws and safe digging practices. The Oregon Utility Notification Center and the laws that it addresses were developed in 1995.

 

For more information, visit the Oregon Utility Notification Center on-line at www.digsafelyoregon.com.

 

Remember, safe digging begins by calling 1-800-332-2344. Call before you dig to keep yourself and vital services safe.

Look for More information on Dig Safely Month activities soon!


::top::


Wednesday, February 27, 2002


For Immediate Release
Contact: Jack P. Dent, (503) 378-6760


Rules Affect Abandoned Utility Lines

Marking abandoned underground lines prevents construction delays and accidents

 

 

SALEM, OREGON - New rules concerning abandoned service lines go into affect on April 1, 2002. The rules will require utility companies, municipalities and other "facility operators" of underground pipelines, service lines, cables, and conduits to mark those lines and to keep records of lines that are declared to be abandoned. The rules were recently adopted by the Oregon Utility Notification Center (OUNC) Board of Directors.

 

Removing unused underground lines is costly and in itself can lead to excavation accidents, so facility operators often abandon the line, leaving it buried and unmarked. According to Jack P. Dent, Chief of Pipeline Safety for the Oregon Public Utility Commission, this practice has caused problems. "If an abandoned line is in the immediate proximity of an in-service line an excavator may not be able to tell which one is in-service. If they don't know that there are actually two lines - one abandoned and one live - their false sense of security can get them into big trouble," says Dent.

 

The new rules under OAR 952-001-0100 require facility operators to mark abandoned facilities at excavation sites. However, the operator is not required to mark the facility as an abandoned facility - the law only requires that the abandoned facility be marked. Abandoned facilities may serve a useful purpose in the future for use as conduits for new facilities, for example, and marking them as abandoned may give excavators the impression that damaging the facility is acceptable. What is important is that the facilities be marked. If an operator does not wish to mark a facility as abandoned, then the facility is marked and treated as an in-service (live) facility.

 

Starting April 1, anyone involved in excavation, including contractors and homeowners, should be aware of the abandoned lines marking procedures. According to the rules, an abandoned facility must be identified with a circle around a capital letter "A" in the same color of paint designated for that type of facility. For example, an abandoned electric line will be marked in red paint with a circled "A" on it.

 

In addition, the rules require operators to keep records that declare lines to be either "Out-of-Service" or "Abandoned" when they have reached the end of their useful life. An "abandoned facility" means an underground facility that is no longer in service and is physically disconnected from the operating facility that is in service. An "out-of-service" facility is one that has not been declared as permanently abandoned and may still be connected to a portion of an operating facility.

 

The abandoned line rules provide for an exemption for service lines - telephone, cable TV, or electric lines - that are located between the facility operator's system and customer's point of service. Just because lines are abandoned does not mean they should be treated poorly. "If abandoned lines are encountered they should be treated with the same level of care as live lines. Often, abandoned lines are put back into service as conduits for cable and fiber optic lines," says Jack Dent.

 

For more information, call the Oregon Public Utility Commission at 503-378-6760 or The Oregon Utility Notification center at 503-232-1987.

 

::top::



Copyright © 2002-2007 Oregon Utility Notification Center. All rights reserved.
The OUNC is an official state agency - www.oregon.gov. To report problems with this site, please email the webmaster.

Site updated and maintained by BentMetal Design